Vanier College Industrial Arts Laboratory Upgrade Project Almost Completed

Vanier College students who use the industrial arts (IA) sector will no longer have to worry about respiratory problems any longer as the school division is modernizing the sector’s dust collection system.

Vanier College students who use the industrial arts (IA) sector will no longer have to worry about respiratory problems any longer as the school division is modernizing the sector’s dust collection system.

Replacing the system has been on the radar at Holy Trinity Catholic School Division since 2016, when a review indicated it would cost $ 250,000 to $ 300,000 to upgrade the dust collection infrastructure. Another review in 2020 revealed an “immediate” need to renovate the school’s IA zone.

A qualified engineer performed a site survey and found several code violations with the dust collector that the school was not tracking, a council report said.

Some violations included the presence of combustible and flammable materials within 15 meters of the welding area; the dust collector did not have an explosion vent directed to the outside; no adequate register return air in zone IA; the collector fan group having no shutdown in the event of fire or explosion; lack of relief valves; and the unit not having a spark detection or extinguishing system.

The division’s buildings department was forced to upgrade several life safety, electrical and mechanical systems based on the engineer’s review, the report continued.

Some changes included adding additional fire sprinklers to the entire area; updating of fire alarms and directional signs; improve lighting, panels, circuit breakers and wiring; the installation of a 10 ton outdoor heating / cooling unit with new or relocated ducts; and remove and reassign the weld area.

The Buildings Department created a revised budget of $ 441,331 – the money came from Holy Trinity’s Preventive Maintenance and Renewal (PMR) account – based on the new code requirements and the ability to improve the learning environment and air quality for the AI ​​lab and adjacent art and music. areas. The updated budget also took into account 19 existing equipment and two new items.

Seven contractors submitted bids, with the highest bid being $ 530,000 and the lowest bid – which was accepted – at $ 437,000, according to the report. The division awarded the contract to Christie Mechanical on May 26, which began work on the project on June 30 and was scheduled to end on October 6.

“Unfortunately, supply chain issues – which every project and contract faces – plagued our project, delaying the two main elements of the project: the dust collector and the RTU (rooftop unit),” the report continues.

The building department expected the last electrical hookups and the concrete slab to be completed by the first week of November, with the RTU to be completed by November 5 and the dust collector by November 9. .

“We only anticipate minor deficiencies which should not disrupt lessons or cause delays,” the report said.

Matt Heisler, facilities manager at Holy Trinity, told the Express that the dust collection system is operational while some pipes still need to be connected. The division expects the project to be officially completed in early December.

“(We) obviously depend on supply chain issues at this point. But other than that, it was quite successful and (we are) very happy to have it, ”he added.

The council report added that the total cost of the project, including professional fees, is estimated at $ 522,121.

The next meeting of the Holy Trinity Education Council will be on Monday December 13th.